Friday, 23 August 2013

Externally British Gas laid the mains and fitted the meters. Northern power grid have commenced on site pulling the mains cable and next week will connect onto the existing services. Internally much the same as last week 2nd fix electrics fitting lights and sockets. Plumbers are connecting the sinks and fitting the showers in blocks 2 and 3, giving the plots a feel of completion with only the final decoration to do.

Friday, 16 August 2013

Externally we are carrying on installing the services, this week was the turn of British Gas to lay their pipework and connect to the plots. Internally in block 1 we continued with the 2nd fix plumbing connecting the baths, basins and toilets. The joiners are coming through fitting the doors and ironmongery. Also the tiling is complete so next week we can fit the sockets and switches. A big thank you for the residents for there patience during the highway works on Rectory View.

Friday, 9 August 2013

Externally Yorkshire Water arrived as planned to installed the water main around site followed next week by British Gas. This will then enable us to back fill the trenches. In block 1 we are continuing 2nd fix M&E fitting the MVHR units and bathrooms. Then the joiners are following boxing in the MVHR units and waste pipes in bathrooms. Next week we are scheduled to start hanging the doors In blocks 2 and 3 the vinyl is complete and the plaster patcher has started snagging the plots ready for final decoration.

Friday, 2 August 2013

We are taking advantage of the good weather and started excavating the service trench around site for the gas and electric. Yorkshire Water are due next week to install the mains run. In block 1 we have completed the plastering and all the kitchens are fitted. We are carrying on with the 2nd fix M&E and 2nd fix joinery. In blocks 2 and 3 we have started to fit the vinyl to the bathrooms.

Friday, 26 July 2013

This week the groundworkers returned to site and started to connect the rainwater pipe gullies. Internally in block 1 we are plastering the last plot and are continuing fitting kitchens, 2nd fix M&E and started tiling the kitchens and toilets. In blocks 2 and 3 we are boxing in the MVHR units and the toilet pipe boxing. Next week we can snag the walls ready for final decoration.
 


 

Tuesday, 23 July 2013

On Block 1 the masonry is complete including the dentil course on the Combs road elevation. Also we completed the render, therefore enabling us to commence stripping the scaffold.
Internally we have started fitting the kitchens and 2nd fix M&E. In Block 3 we have hung the doors and fitted the ironmongery and started hanging the doors in Block 2.